Major source permits have a 30-day public comment period followed by a 45-day EPA review period. Federal (40 CFR 70.8 (d)) and State (OAC 252:100-8-8 (j)) regulations provide a 60-day period after the expiration of the EPA 45-day review period in which the public may petition EPA based on objections raised within the public comment period.
For your convenience, a list of all the major source permits currently (or scheduled to be) open to petition along with their petition start and end dates are given below.
Permit Number | Company Name | Facility Name | County | Petition Start Date | Petition End Date |
---|---|---|---|---|---|
2024-0462-TVR3 | OWENS BROCKWAY GLASS CONTAINER INC | MUSKOGEE | MUSKOGEE | 2025-04-14 | 2025-06-13 |
2023-0870-TVR4 | BIMBO BAKERIES USA INC | OKLAHOMA CITY BAKERY | OKLAHOMA | 2025-04-15 | 2025-06-14 |
2024-1082-TVR4 | CARDINAL FG CO | CARDINAL GLASS PLANT | BRYAN | 2025-04-19 | 2025-06-18 |
2022-0425-TV | TARGA PIPELINE MIDCONTINENT LLC | KETCHUM RANCH COMPRESSOR STATION | STEPHENS | 2025-04-19 | 2025-06-18 |
2023-0960-TVR3 M-1 | ANCHOR GLASS CONTAINER CORP | HENRYETTA FACILITY | OKMULGEE | 2025-04-22 | 2025-06-21 |
2014-1722-TVR M-2 | REWORLD TULSA LLC | REWORLD TULSA LLC | TULSA | 2025-04-29 | 2025-06-28 |
2015-0643-TV | COMMERCIAL METALS CO | CMC STEEL OKLAHOMA | BRYAN | 2025-05-03 | 2025-07-02 |
2022-0106-TVR4 | DCP OPERATING CO LP | BEAVER COUNTY 2 COMPRESSOR STATION | BEAVER | 2025-05-12 | 2025-07-11 |
2024-0107-TVR4 | AMERICAN GYPSUM CO LLC | GYPSUM WALLBOARD PLANT | JACKSON | 2025-05-18 | 2025-07-17 |
2023-0802-TVR3 | PONCA CITY CITY OF | PONCA CITY LANDFILL | KAY | 2025-05-26 | 2025-07-25 |
2024-0349-TVR3 | AMERICAN CASTING LLC | AMERICAN CASTING | MAYES | 2025-05-29 | 2025-07-28 |
2016-1066-TV | KEYERA ENERGY INC | WILDHORSE TERMINAL | LINCOLN | 2025-05-31 | 2025-07-30 |
2025-0002-TVR4 | PUBLIC SERVICE COMPANY OF OKLAHOMA | PSO WELEETKA POWER STATION | OKFUSKEE | 2025-06-02 | 2025-08-01 |
2023-0135-C M-1 | OKLAHOMA LNDFLL HOLDINGS INC | SOUTHERN PLAINS LANDFILL | GRADY | 2025-05-18 | 2025-07-17 |
2021-5061-C M-3 | ONETA POWER LLC | ONETA POWER LLC | WAGONER | 2025-05-31 | 2025-07-30 |